We are working with Cadent to design and relocate the Gas Pressure Reduction System (GPRS), which is currently located on the old gas works site. This will enable housing delivery on the site.

The proposed new location of the Gas Pressure Reduction System is on land to the south of the active Hill Road Allotments.

Cadent submitted a planning application for this in February 2022, with the reference 22/00239/FUL.

We granted planning permission in May 2022.

Timings

Works are now underway, with the following planned programme.

These dates may be subject to change and we will update these as works progress.

Phase 01
Phase
Phase 01
Activity
Mobilisation and site establishment
Start
Complete
Finish
Phase 02 and 03
Phase
Phase 02 and 03
Activity
GPRS civil works
Start
Mar-23
Finish
Aug-26
Phase 04
Phase
Phase 04
Activity
GPRS mechanical works
Start
May-24
Finish
May-26
Phase 05
Phase
Phase 05
Activity
GPRS electrical and instrumentation works
Start
Jul-25
Finish
May-26
Phase 06 and 07
Phase
Phase 06 and 07
Activity
Meadow pipeline operations
Start
Dec-23
Finish
Jun-26
Phase 08
Phase
Phase 08
Activity
Commissioning
Start
May-26
Finish
May-26
Phase 09
Phase
Phase 09
Activity
Wharf Road Governor Installation
Start
Complete
Finish
Phase 10
Phase
Phase 10
Activity
Decommission Old GPRS
Start
Jun-26
Finish
Aug-26
Phase 11
Phase
Phase 11
Activity
Fence and civil works
Start
Nov-25
Finish
Aug-26
Phase 12
Phase
Phase 12
Activity
Demobilisation
Start
Finish
Aug-26
Phase Activity Start Finish
Phase 01 Mobilisation and site establishment Complete
Phase 02 and 03 GPRS civil works Mar-23 Aug-26
Phase 04 GPRS mechanical works May-24 May-26
Phase 05 GPRS electrical and instrumentation works Jul-25 May-26
Phase 06 and 07 Meadow pipeline operations Dec-23 Jun-26
Phase 08 Commissioning May-26 May-26
Phase 09 Wharf Road Governor Installation Complete
Phase 10 Decommission Old GPRS Jun-26 Aug-26
Phase 11 Fence and civil works Nov-25 Aug-26
Phase 12 Demobilisation Aug-26

Key dates

Commission GPRS
Activity
Commission GPRS
Start
Complete
Finish
Construction works in the vicinity allotment
Activity
Construction works in the vicinity allotment
Start
Jan-23
Finish
Aug-26
District Governor Construction works on Wharf Road, Taylor Wimpey
Activity
District Governor Construction works on Wharf Road, Taylor Wimpey
Start
Complete
Finish
Meadow cyclepath diversion
Activity
Meadow cyclepath diversion
Start
Mar-23
Finish
Aug-26
Temporary allotment access arrangements
Activity
Temporary allotment access arrangements
Start
Jan-23
Finish
Aug-26
Wharf Road - Phase 1
Activity
Wharf Road - Phase 1
Start
Complete
Finish
Wharf Road - Phase 2
Activity
Wharf Road - Phase 2
Start
Complete
Finish
Wharf Road - Phase 3
Activity
Wharf Road - Phase 3
Start
Complete
Finish
Activity Start Finish
Commission GPRS Complete
Construction works in the vicinity allotment Jan-23 Aug-26
District Governor Construction works on Wharf Road, Taylor Wimpey Complete
Meadow cyclepath diversion Mar-23 Aug-26
Temporary allotment access arrangements Jan-23 Aug-26
Wharf Road - Phase 1 Complete
Wharf Road - Phase 2 Complete
Wharf Road - Phase 3 Complete

Is there something wrong with this page?

You can report issues with the website using our website feedback form, which will go directly to the Web Team. This team will be unable to deal with your enquiry if it is not related to the website.