We are working with Cadent to design and relocate the Gas Pressure Reduction System (GPRS), which is currently located on the old gas works site. This will enable housing delivery on the site.

The proposed new location of the Gas Pressure Reduction System is on land to the south of the active Hill Road Allotments.

Cadent submitted a planning application for this in February 2022, with the reference 22/00239/FUL.

We granted planning permission in May 2022.

Timings

Works are now underway, with the following planned programme.

These dates may be subject to change and we will update these as works progress.

Phase Activity Start Finish
Phase 01 Mobilisation and site establishment Complete
Phase 02 and 03 GPRS civil works 10 March 2023 03 November 2025
Phase 04 GPRS mechanical works 06 January 2025 06 October 2025
Phase 05 GPRS electrical and instrumentation works 07 March 2025 29 July 2025
Phase 06 and 07 Meadow pipeline operations 04 February 2025 09 December 2025
Phase 08 Commissioning 30 April 2025 09 December 2025
Phase 09 Wharf Road Governor Installation 09 May 2025 09 July 2025
Phase 10 Decommission Old GPRS 27 October 2025 04 December 2025
Phase 11 Fence and civil works 04 November 2025 20 January 2026
Phase 12 Demobilisation 18 February 2026 20 February 2026

Key dates

Activity Start Finish
Commission GPRS 26 September 2025 9 October 2025
Construction works in the vicinity allotment 26 January 2023 9 December 2025
District Governor Construction works on Wharf Road, Taylor Wimpey 9 May 2025 9 July 2025
Meadow cyclepath diversion 29 March 2023 9 December 2025
Temporary allotment access arrangements 26 January 2023 9 December 2025
Wharf Road - Phase 1 Complete
Wharf Road - Phase 2 Complete
Wharf Road - Phase 3 20 February 2025 20 May 2025

Is there something wrong with this page?

You can report issues with the website using our website feedback form, which will go directly to the Web Team. This team will be unable to deal with your enquiry if it is not related to the website.