Chelmsford City Council

Local Plan Examination

The Independent Examination hearing sessions ended on 13 December 2018.

You can still view the draft hearings timetable setting out the programme for the hearing sessions.

You can view the documents for each week of the examination, as well as Statements of Common Ground, other documents and the submission documents.

We will add any updates from the Inspector or other new documents as we receive them, under the Post hearing documents tab. 

The Inspector

The Secretary of State appointed Yvonne Wright BSc (Hons) DipTP MSc DMS MRTPI as the inspector.

The Independent Examination hearing sessions took place in November and December 2018. You can view the Examination documents, including the programme, agendas and guidance notes by expanding the tabs. 

We anticipate the Inspector will issue her report early next year. 

She will apply tests of soundness, which assess if:

  • we have prepared the Local Plan in accordance with the Duty to Co-operate
  • the Local Plan is legally compliant
  • the Local Plan is consistent with national policy

 We will add any updates from the Inspector or other new documents as we receive them, under the Post hearing documents tab.   

The Programme Officer

We have appointed a Programme Officer, an independent officer who will organised and manage the administrative and procedural matters of the Examination.

Our Programme Officer is Andrea Copsey.  

For any queries about the Local Plan Examination, you can contact Andrea:


What the Local Plan includes

The draft Local Plan includes:

  • around 8,800 houses on new site allocations
  • around 1,300 houses on sites not identified (windfalls)
  • around 11,700 new homes which already have planning permission
  • 10 Gypsy and Traveller pitches
  • 24 Travelling Showpeople plots
  • 725 new jobs a year
  • 55,000 square metres of business and employment space
  • protection for the green belt, valued landscapes, heritage assets, and areas for wildlife and nature conservation
  • supporting infrastructure including schools, roads, transport improvements, and community and leisure facilities
  • planning polices which we will use to determine planning applications

  

Evidence base

The evidence base contains the background and technical documents we used to prepare the Local Plan. These include housing, traffic, landscape and sustainability. We have also been working with our partners to understand infrastructure needs.

  

Consultation stages

We have carried out three stages of consultation on the Local Plan.

  • Issues and Options, from November 2015 to January 2016
  • Preferred Options, from March 2017 to May 2017
  • Pre-Submission, from January 2018 to March 2018

We carefully considered all the comments we received in these consultations, and used them to progress the Local Plan to submission stage.

You can:


We will produce a number of documents to help the examination. We will publish these documents as we create them, with the newest at the top of the list.
  

ReferenceDocumentAuthorDateNotes
EXHS012bHearing Statement: Grosvenor Developments Ltd and Hammonds Estates LLP, Matter 1 (2 of 2)Grosvenor Developments Ltd and Hammonds Estate LLP13 November 2018 
EXHS012aHearing Statement: Grosvenor Developments Ltd and Hammonds Estates LLP, Matter 1 (1 of 2)Grosvenor Developments Ltd and Hammonds Estate LLP13 November 2018 
EXHS034Hearing Statement: Bloor Homes Eastern, Matters 2 and 5Bloor Homes Eastern13 November 2018 
EX016Hearing Statement: Chelmsford City Council, Week 1, Matter 5 (Spatial Strategy)Chelmsford City Council9 November 2018 
EX015Hearing Statement: Chelmsford City Council, Week 1, Matter 4 (OAEN)Chelmsford City Council9 November 2018 
EX014Hearing Statement: Chelmsford City Council, Week 1, Matter 3 (OAHN)Chelmsford City Council9 November 2018 
EX013Hearing Statement: Chelmsford City Council, Week 1, Matter 2 (Strategic Priorities, Vision, Spatial Principles)Chelmsford City Council9 November 2018 
EX012Hearing Statement: Chelmsford City Council, Week 1, Matter 1 (Statutory Procedures and Legal Matters)Chelmsford City Council9 November 2018 
EXHS001Hearing Statement: Aquila Developments Ltd, Matter 4Aquila Developments Ltd9 November 2018 
EXHS002Hearing Statement: Bovis Homes, Matter 5Bovis Homes9 November 2018 
Note 1: We have published additional site spreadsheet information for Appendix G of the Pre-Submission Local Plan SA Report (SD 004). This is to ensure that all the completed detailed site SA spreadsheet information is published.


ReferenceDocumentAuthorDate
EX 031Chelmsford Racecourse Noise Complaints NoteChelmsford City Council5 December 2018
EX 030EX030 North Essex Authorities: Further Response from Inspector (IED014)Mr Roger Clews 27 November 2018
EB 063BDevelopment Trajectory: Beaulieu, Channels and proposed North East Chelmsford (SGS4) sites, November 2018 updateChelmsford City CouncilNovember 2018
EB 063AHousing Site Schedule Updated Format November 2018 with Annual Projections to 2035-36Chelmsford City CouncilNovember 2018
EX 025Housing Implementation StrategyChelmsford City CouncilNovember 2018
EX HS067Hearing Statement – Chris Gutteridge – Matter 6aChris GutteridgeNovember 2018
EX HS066JHearing Statement: Hopkins Homes (Matter 6a, 10 of 10)Hopkins HomesNovember 2018
EX HS066IHearing Statement: Hopkins Homes (Matter 6a, 9 of 10)Hopkins HomesNovember 2018
EX HS066HHearing Statement: Hopkins Homes (Matter 6a, 8 of 10)Hopkins HomesNovember 2018
EX HS066GHearing Statement: Hopkins Homes (Matter 6a, 7 of 10)Hopkins HomesNovember 2018

ReferenceDocumentAuthorDate
EXHS099Hearing Statement - Taylor Wimpey Strategic Land - Matter 9Taylor Wimpey Strategic land23 November 2018
EXHS098Hearing Statement - South Woodham Ferrers Town Council - Matter 6cSWF TC23 November 2018
EXHS097Hearing Statement - Seven Capital plc - Matter 10Seven Capital plc23 November 2018
EXHS096Hearing Statement - Redrow Homes - Matter 11Redrow Homes23 November 2018
EXHS095Hearing Statement - Redrow Homes - Matter 10Redrow Homes23 November 2018
EXHS094Hearing Statement - Redrow Homes - Matter 9Redrow Homes23 November 2018
EXHS093Hearing Statement - Redrow Homes - Matter 8Redrow Homes23 November 2018
EXHS092Hearing Statement - North East Chelmsford Garden Village Consortium - Matter 11North East Chelmsford Garden Village Consortium23 November 2018
EXHS091Hearing Statement - North East Chelmsford Garden Village Consortium - Matter 8North East Chelmsford Garden Village Consortium23 November 2018
EXHS090Hearing Statement - North and West Parishes Group - Matter 9North and West Parishes Group23 November 2018

ReferenceDocumentAuthorDate
SOCG26Statement of Common Ground with Broomfield Parish CouncilChelmsford City Council, Broomfield Parish CouncilDecember 2018
SOCG14CStatement of Common Ground with West Chelmsford: Strategic Matters Chelmsford City Council, Crest Nicholson December 2018
PSD004Response to SOCG15 - Decision Notice 2Grosvenor Developments Ltd and Hammonds Estates LLPNovember 2018
PSD003Response to SOCG15 - Decision Notice 1Grosvenor Developments Ltd and Hammonds Estates LLPNovember 2018
PSD002Response to SOCG15 - Scoping OpinionGrosvenor Developments Ltd and Hammonds Estates LLPNovember 2018
SOCG24Statement of Common Ground Proposed Station at Beaulieu (NE Chelmsford)Chelmsford City Council, Essex County Council, Network Rail, Greater Anglia, Countryside Zest November 2018
SOCG23Statement of Common Ground with Mid-Essex Hospital Trust and ECCChelmsford City Council, Essex County Council, Mid Essex Hospital TrustNovember 2018
SOCG22Statement of Common Ground with Highways England & ECCChelmsford City Council, Essex County Council, Highways EnglandNovember 2018
SOCG21Statement of Common Ground with North East Chelmsford (Strategic Matters)Chelmsford City Council, Essex County Council, The North East Chelmsford Garden Village ConsortiumNovember 2018
SOCG20BStatement of Common Ground with Site Promoters of SWF (Highwys and Transport)Chelmsford City Council, Essex County Council, Countryside, Speakman FamilyNovember 2018

We sent these Submission Documents to the inspector on 29 June 2018:

We also sent a range of:

  • evidence base documents
  • topic papers
  • statements of common ground

 

You can look at our evidence base to download and view these documents.

 

Viewing the documents

You can download and view the Submission Documents from the list. Some of the documents are large in size. You may find it easier to download these documents on a desktop computer, rather than on a smartphone or tablet.

You can also view the Submission Documents at:

  

Local Development Scheme

We have set out what Local Plan documents we will prepare and a timetable in our  Local Development Scheme.

  

Statement of Community Involvement

Our  Statement of Community Involvement sets out how and when community involvement will take place, and what organisations and individuals we will consult.

  

Our newsletters

Each of our newsletters gives an overview of the different stages of developing the new Local Plan.

You can download our:

  

Mandatory field